Home>>Production process>>production Process

Model car development of the production process

A, development process

1. Collect original material, including true car photographs, production requirements, adornment material, etc

2. According to true car photo and requirements of making buildings made by hand to do, and modified car proportion into true verification, the rights to fit

3. Hand do begin 3D copy after approval in accordance with the number, design department on hand parting, do change figure, and establish the 2D mould figure

4. Mould department according to the drawing work for ordering materials, manufacturing work mode

5. Work after the completion of the mould making, product engineers arrangement first try mold, production fixture (including blunt shuikou fixture, pad printing film injection mould, assembly, and according to fit fixture) packaging solution and arrange the design requirement for play to do

6. The product engineering changing outfits after the structure and the coordination problems are analyzed, and prepare to die mould department chart and improved work mould

7. Finish first after improving mould department namely arrange a second try mode, and according to the arrangement of jig made, and sample for manufacturing EP into qa department for inspection, testing, another 2PCS sample fit into the review

8. Engineering in manufacturing EP do process constantly collect each production department opinion and arrange improve tooling/fixture and production process. Engineering in EP stage of proposed buildings, comprehensive each production department opinion and to make the effectively improve arrange namely after the final project do FEP offices), production (2PCS sample and return to investors may endorse.

9. Engineering in sign after receiving buildings do in that meeting, held put distributed sign do and engineering material

10. In meetings, held in planning put that make relevant products, each department namely scheduling entering the product production status.

Second, the production process

1. Molding department according to worker mould material molding production, including beer, plastic, the pruning, classification, and pay the next department or faithfully

2. Die-casting parts according to work on die-casting mould material production, including die-casting, FenShuiKou, batch feng, thick polishing treatment, after the completion of the production of electrostatic department

3. According to the sign of electrostatic department do big color and engineering material for electrostatic spraying production, including alloy parts pretreatment, electrostatic spraying, handmade painting, fine polishing and waxing etc, complete production into the next department after

4. According to the ministry of oil, do and engineering material arrangement signed injection, including DaQiang spraying, fine gun spray paint, artificially holding after such as color, complete production into the next department

5. Moving printing department according to do and adornment material arrangement signed pad printing production, including monochromatic pad printing, double-color, four color or six colors pad, hand hold color, after completion of the production into assembling department

6. Purchasing according to the engineering material arrangement electroplating bei pieces outside sends production; Purchasing hardware, packaging materials, including screw, electrical erosion slice, spring, color box, foam rubber, outside the box, etc

7. The assembly department according to sign do, including engine arrange production assembly, underneath the car assembly, inside seat assembly, table plate assembly, finished product assembly and finished product packaging, complete production arranged namely after faithfully.

 
Previous program:Mdel product final test Next program:none